Past
projects:
Project:
University of Alaska Anchorage
Window Replacement
Date: July 2006 - September 2006
Owner: University of Alaska
Location: Anchorage, Alaska
Replace
all windows in six (6) buildings in the University
of Alaska, Anchorage’s Main Apartment Complex
(MAC). |

|


|
Title:
Abate Central Power Plant
Date: October 2005 - April 2006
Owner: US Air Force – Elmendorf Air Force Base
Location: Anchorage, Alaska
Synopsis: Remove Thermal Surface Insulation from a
four-leveled concrete and steel, 127,762 square foot
structure during winter months.
|
|
Title:
Abate 74 Steam Pits
Date: June 2004 - November 2005
Owner: US Air Force – Elmendorf Air Force Base
Location: Anchorage, Alaska
Synopsis: Removal of Thermal Surface Insulation from
74 steam pits and disposing of over 412 cubic yards
of ACM. |
NO
PHOTO AVAILABLE |
|


|
Title:
Demolish Tank Farm 1
Date: April 2005 - October 2005
Owner: US Air Force – Elmendorf Air Force Base
Location: Anchorage, Alaska
Synopsis: Work included removal of Thermal Surface Insulation,
lead based paint abatement in a base pump house as well
as the demolition of a 600 square foot pump-house, 3-50,000
gallon tanks, backfilling with base material, demolishing
two abandoned pits, disconnecting utilities, demolishing
truck-fill-stand and paving at fill-stand, pump-house
and tank site.
|
|
Title:
Fort Wainwright Base Theater
Date: August 2004 - August 2004
Owner: Directorate of Contracting, Fort Wainwright
Location: Fairbanks, Alaska
Synopsis: Conducted site survey, environmental assessment,
sampling and analysis of all Class 1 and Class 2 Asbestos
Containing Materials (ACM) and removal of Thermal Surface
Insulation and CAB from a military base theatre in preparation
for demolition.
|
NO
PHOTO AVAILABLE |
|
 |
Title:
Abate Dimond High School
Date: June 2004 - July 2004
Owner: Anchorage School District
Location: Anchorage, Alaska
Synopsis: Removal of Thermal Surface Insulation and
Cement Asbestos Board from a 41,302 square foot K-12
educational facility.
|
|
Title:
Demolish Various Buildings, Fort Wainwright
Date: April 2003 - October 2003
Owner: Directorate of Contracting, Fort Richardson
Location: Fairbanks, Alaska
Synopsis: Conducted site survey, environmental assessment,
sampling and analysis of all Class 1 and Class 2 Asbestos
Containing Materials (ACM) and provided consultation
and project management services for ACM abatement for
various buildings prior to demolition.
|
 |
|
|
 |
|